Cookie Control

This site uses cookies to store information on your computer.

Some cookies on this site are essential, and the site won't work as expected without them. These cookies are set when you submit a form, login or interact with the site by doing something that goes beyond clicking on simple links.

We also use some non-essential cookies to anonymously track visitors or enhance your experience of the site. If you're not happy with this, we won't set these cookies but some nice features of the site may be unavailable.

By using our site you accept the terms of our Privacy Policy.

(One cookie will be set to store your preference)
(Ticking this sets a cookie to hide this popup if you then hit close. This will not store any personal information)

"Federal Judge Tosses Out BLM Approval of Nev.'s Largest Project"

"A federal judge in Nevada has thrown out the Obama administration's approval of what was projected to be the Silver State's largest wind power project, ruling that the Interior Department did not properly evaluate potential impacts to golden eagles and Mojave Desert tortoises.

U.S. District Judge Miranda Du's seven-page order issued late Friday is a sharp rebuke of the final environmental impact statement (EIS) for the 200-megawatt Searchlight Wind Energy Project conducted by the Bureau of Land Management and a biological opinion conducted by the Fish and Wildlife Service. Former Interior Secretary Ken Salazar signed a record of decision formally approving the project in March 2013.

Legal experts say this is the first time a court has formally ruled invalid a final EIS, biological opinion and record of decision for a renewable energy project."

Scott Streater reports for Greenwire November 4, 2015.

Source: Greenwire, 11/05/2015